    An investment at the Port of Gdansk nearing completion

    The Port of Gdansk says an investment is nearing completion with 85% of the work already having been already executed. The NDI company will complete work on the redevelopment of the road and railway system at the Port of Gdansk. The ongoing work will result in 5.6 km of new roads, 16 junctions, 4 flyovers, and a buffer car park for heavy goods vehicles.

    An additional railway track leading to the DCT terminal has already been completed, along with new tracks leading to the coal terminals, and a modern railway traffic control system.

    The last land reinforcements, consisting in placing CFA piles in the ramp leading to the WD-4 facility, have been completed, and earthwork is still in progress there. After completing the road surface work on the new roadway of Kontenerowa street, the contractor, NDI, is preparing to switch the traffic and redevelop the existing roadway. It will be the last stage of the works. The construction of the WD-2 flyover, along with the ramps, has been completed. 95% of network work within the main collector sewers for rainwater has been executed and the redevelopment of the last sections of streets located within the port, that is Budowniczych Portu Polnocnego (right lane), mjr. H. Sucharskiego, and kpt. W. Poinca streets, has started.

    Some rather impressive and interesting work is under way at Portowa street, where a car park with a concrete surface for heavy goods vehicles is being constructed.

    "We are at the stage of preparing the 27 cm thick concrete surfaces," says Maciej Szymanski, construction site manager, NDI. "The car park has a surface area of 15,000 square metres and its volume is 4,700 cubic metres of class C40/50 high strength concrete. Due to the investor's high strength and quality requirements, we had to adjust the method of laying the concrete mix using the sliding method. The method consists in the use of a machine which can lay the concrete, thicken it, vibrate the dowel bars and anchors, and float the concrete - all during one cycle. The machine performs four actions at the same time, which, if performed manually, would require about 30-40 workers and we would not be sure whether the surface would have the required quality," adds Maciej Szymanski.

    "We are happy with the progress of the work and very pleased that we are nearing completion of such an important undertaking. The investment currently under way will streamline road and railway traffic within the part of the road system used to get to external terminals, primarily the DCT, Sea-Invest, and Gaspol terminals," says Lukasz Greinke, President of the Port of Gdansk Authority.

    The method used by NDI also finds application in the construction of both airports and motorways. It allows us to obtain the required degree of thickness across the entire cross section of the surface, 27 cm in this specific case.
    The machine used here makes it possible to prepare up to 15,000-20,000 square metres of surface a month, which amounts to 150,000 square metres per year, taking into consideration adverse weather conditions.

    As part of the road and railway network expansion project at the Outer Port, executed by NDI for the Port of Gdansk, the following streets will be converted: Portowa, Poinca, Kontenerowa, and Budowniczych Portu Polnocnego, with the total length of 5.6 km. Four new flyovers are under construction and two existing ones will be demolished (including one over railway tracks in operation and one over PERN, LOTOS, and Naftoport fuel pipelines). Another railway track leading to the DCT terminal will be added, along with new tracks leading to the coal terminals, and a modern railway traffic control system will be implemented. The first buffer car park for heavy goods vehicles in this part of the port will also be built. The investment, worth over PLN 176 million, is being executed by the NDI company from Sopot.

     




2020 June 5

18:21 Mezhregiontruboprovodstroy appointed as sole contractor for construction of Utrenny terminal
18:05 CMA CGM announces FAK rates from Europe to Indian Ocean Islands
17:35 Teesport welcomes largest containership
17:05 EUROGATE Intermodal appoints Christopher Beplat as a new managing director
16:50 Russian Railways: Loading of export cargo bound for domestic ports up 6.4% in May 2020
16:35 DNV GL performs over twenty remote wind turbine inspections globally in times of COVID-19 related-travel restrictions
16:05 Gasum performs first LNG bunkering to Heerema’s Sleipnir
15:28 Acquisition and recapitalisation of Royal IHC finalised
14:18 First of two Austal's 118 metre trimarans for Fred. Olsen completes sea trials in Australia
13:56 Rosmorrechflot announces new competition for construction of Bagayevsky hydrosystem
13:29 Zvezda Shipyard stars cutting steel for yet another Aframax tanker
13:01 Keppel enters into framework deed with Borr Drilling to defer scheduled delivery of rigs
12:01 Port of Rotterdam Authority decides to hold RFT for transport service along Container Exchange Route
11:47 Yevgeny Ditrikh takes helm of STLC Board of Directors
11:04 The second largest container vessels in the world, now has its “Socarrat”
10:41 Oil prices rise within $1
10:28 Marseille Maersk sets up new record for the port of Rotterdam
10:23 Training exercise held with rescuers of RF Navy’s Northern fleet to assist emergency ship in the Arctic
10:00 RF Navy's oceanographic research vessel Admiral Vladimirsky entered the North Sea
09:39 Bunker prices rise at the port of Saint-Petersburg, Russia
09:18 Baltic Dry Index on June 4
08:46 MABUX: Bunker market this morning, June 05

2020 June 4

18:20 Wärtsilä to supply Europe's most modern simulator for inland shipping training
18:02 Dutch innovative app trains 10,000 process industry workers in Singapore during Covid-19 lockdown
17:47 Singapore Maritime and Ports Authority issues guidelines for crew change
17:25 Gasum performs first LNG bunkering to Heerema’s Sleipnir
17:02 China Merchants Group's emergency working group of the prevention and control of COVID-19 holds 20th meeting
16:34 Throughput of port Vysotsk in 5M’2020 fell by 24.2% Y-o-Y
16:02 Diana Shipping announces time charter contract for m/v G. P. Zafirakis with Koch
15:41 NS Power's crew rescues two people in the Andaman Sea
15:23 RS Rules update: hybrid propulsion
15:02 Grimaldi boosts its Italy-Greece connections
14:32 DNV GL and ABB launch new MOU to advance marine digitalization with a remote signing ceremony
14:02 150 trapped eels rescued at the Port of Gothenburg
13:48 Bunker price are stable at the Far East ports of Russia (graph)
13:31 MSC Mediterranean Shipping Company extends the seasonal blanking programme on its Asia–Europe network
13:01 Wärtsilä offers new remote service to overcome Covid-19 travel restrictions
12:31 DEME to build the Scheldt tunnel
12:03 Havyard presents new design concept for zero-emission sightseeing vessels
11:45 Annual throughput of Murmansk Transport Hub to be raised to 100 million tonnes
11:23 Construction of automated gate complex commences at APM Terminals Aarhus
11:10 Port of Zeebrugge joins the International Port Community Systems Association
10:58 Jiangnan Shipyard and Gabadi teams complete construction of the first LNG tank as part of an LNG-fuelled container ship project
10:57 AS Tallink Grupp Statistics for May 2020
10:33 More departures added for Helsinki-Tallinn route vessel Star from 4 June 2020
10:11 Oil prices go down by 1.48%-2.06%
10:00 CMA CGM cancels Low Sulphur Surcharge from July 1st, 2020
09:52 Russia’s leading shipping companies suggest development of ATB services by the USA example
09:40 PIER71 launches Smart Port Challenge 2020 with New Venture Capital Partners for maritime tech start-ups investments
09:36 MABUX: Bunker market this morning, June 04
09:14 Baltic Dry Index on June 3

2020 June 3

18:25 Russia's Main Department of State Expertise approves construction of operational water area under Obskiy LNG project
18:03 Cargotec’s Kalmar and MacGregor to help drive development of connected automated waterborne transport through participation in AEGIS project
17:46 Rosmorport announced tender to reconstruct coastal facilities of Vanino-Kholmsk ferry service
17:24 RF Government approved allocation of RUB 60.5 billion for Russian Railways’ BAM and Transsib projects in 2020
17:02 THE Alliance announces COVID-19 response measures for July, August and September 2020
16:35 Russian Railways CEO says railway link with Murmansk to be restored by June 23
16:11 Transport route to link Quy Nhon Port with Northeast Asia
15:49 Rosatomflot completed escorting Vladimir Voronin gas carrier along the Northern Sea Route
15:33 Fincantieri and ENI extend an agreement in the field of circular economy and decarbonisation