    Maximising monopile and transition piece transport for DEME Offshore

    There is no such thing as a standard job in the heavy lift and project transport industry. Every contract and every client is unique – and this requires maritime service providers like Jumbo-SAL-Alliance to deliver versatility and flexibility at every turn.

    Jumbo’s monopile and transition piece transport for DEME Offshore is great example of such a project. The flexibility being provided by the heavy lift vessel Fairmaster, and the versatility coming from Jumbo’s vessel crews and onshore engineers who planned and executed the project with a true ‘total solution’ mindset.

    Biggest job to date
    Take a quick look at the specs of this project and you would be forgiven for thinking that this was a straightforward ‘back and forth’ vessel charter contract. After all, the scope involved 37 voyages from Rostock, Germany and Aalborg, Denmark to Eemshaven, the Netherlands in under a year.

    However, upon closer inspection, it is clear that Jumbo’s work for DEME Offshore for Ørsted’s Hornsea Two offshore wind farm was by no means straightforward. For a start, the sheer number of offshore wind farm components was large: totalling 141 monopiles (MPs) and 131 transition pieces (TPs). All these needed to be loaded, transported, and unloaded.

    Next up, the dimensions of the components were substantial (considering the fact that wind turbine generators – WTGs – are getting bigger and bigger, it is only logical that their foundations need to increase in size too). Furthermore, the MPs and TPs were of various sizes; the TPs all had a 6.5-metre diameter and weighed 345 tonnes, but the MPs ranged from 8.3 metres to 9.5 metres in diameter and from 775 to 1,285 tonnes.

    Smart supply chain link
    This diversity of cargoes meant that Jumbo had to bring in the right vessel for the job. Its K-3000 class heavy lift vessel Fairmaster fit the bill perfectly. This 152.9 metre-long heavy lift vessel, with two 1,500-tonne cranes, provided a flexible deck layout that enabled compliance with the project’s schedules.

    The Fairmaster’s flexibility allowed Jumbo’s engineering teams to devise three different loading configurations: five MPs loaded on deck and in the hold, six TPs and three MPs, or three TPs and four MPs. This in turn yielded benefits higher up the project’s supply chain: Jumbo could adjust to its client’s sailing sequence, which was linked to the delivery sequence from its fabrication yards.

    “We converted the Fairmaster into a kind of ‘Swiss Army knife’ that provided an unrivalled heavy lift vessel intake of large diameter monopiles and transition pieces,” says Jumbo commercial manager Boudewijn van der Garden.

    Maxing the carrying capacity
    In a multi-voyage project like this, efficiency is key. You could say that the aim of the game is to carry the most equipment within the least amount of time. To this end, Jumbo used the planning phase to design and engineer MP saddles and TP grillages that utilised the Fairmaster’s carrying capacity to the max. Using inlays in the saddles to accommodate the different diameters of the MPs, the resulting clearances between components were tight: sometimes 50cm or less.

    To speed up loading and unloading operations, Jumbo installed project-specific lifting lugs onto the Fairmaster’s deck hatches. This relatively simple, yet smart and well-timed, idea is an example of what Jumbo calls its ‘value engineering proposals’ that are presented to clients to optimise operations.

    Biofuel initiative
    Responding to Ørsted’s goal of decreasing the environmental footprint of the construction on the Hornsea Two wind farm, Jumbo included a Green Initiative into its project execution. This was to sail with Bio-Fuel Oil from sustainable marine biofuel provider GoodFuels, delivering an expected 80-90% CO2 reduction versus fossil equivalents, and zero sulphur oxide (SOx) emissions.

    Every lift a heavy lift
    The Hornsea Two project is notable for Jumbo in that it was the largest number of MPs and TPs that it has ever shipped in a single contract. Because of the repetitive nature of the job, the company paid special attention to maintaining a clear focus on safety throughout the project. Jumbo’s vessel crews treated every lift as a heavy lift with a high focus on bringing these major cargoes safely on board. In fact, Jumbo brought in an external safety consultant to investigate and prevent complacency on board.

    Jumbo’s ‘best-for-project’ focus during the project planning and execution optimised every part of this extensive transport scope. “Our flexible engineering on this project is one of the things we’re most proud of – it helped us conclude the project scope within just 37 voyages in a period of just under twelve months,” concludes Jumbo’s project manager Maarten De Gruyter.




2024 March 28

18:05 Jan De Nul, ENGIE and Equans launch a pilot project centred around the use of Vanadium Redox Flow batteries
17:35 Latvian port equipment manufacturer Bleste introduces new bulk handling ‘bucket’
17:05 Investors upgrade Navios Maritime Partners
16:25 DEME reports 22% increase in the orderbook and a record-high turnover of 3.3 billion euros in 2023
16:14 MABUX: Bunker Outlook, Week 13, 2024
15:41 AD Ports Group announced the opening of Saadiyat Marina & Ferry Terminal and Rabdan Marina
15:11 Sydney invests $11.5 million in two new operational vessels designed by Incat Crowther
14:55 China’s Jinzhao wins Peru $405m port construction contract
14:13 APM Terminals Moín handled six million TEU
13:48 ClassNK grants Innovation Endorsements for Products & Solutions to two innovative initiatives by MOL
13:37 Konecranes launches its flagship Konecranes X-series industrial crane
12:53 United European Car Carriers UECC spearheads collaboration with industry leaders to advance CNSL as a sustainable marine fuel
12:26 Ocean Network Express announces Transpacific service
11:48 Yang Ming announces 2025 Trans-Pacific service network
11:24 Fincantieri signs contract for the supply of two PPAs to Indonesia
10:42 Maersk transported more than 660,000 TEU using clean fuel in 2023
10:23 Documentation delays push industry costs to $3bn
09:48 PONANT and FARWIND Energy partner to develop green hydrogen refueling solutions

2024 March 27

18:22 Bureau Veritas awards world’s first prototype certification for SolarDuck’s floating offshore solar solution
17:58 The recently converted Allseas's shallow water pipelay barge starts preparations for its first commercial project
17:38 The Port of Rotterdam calls on the European Commission and Parliament to focus on actively promoting green energy
15:23 SEFE to become sole shareholder of WIGA
14:53 Ocean Installer secures yet another SLM contract with Equinor
14:23 Cadeler signs offshore wind turbine installation contract for the vessel Wind Scylla
13:42 Carnival Cruise Line orders 5th Excel-class cruise ship
13:11 Maersk and MSC overcharging cargo owners for EU ETS, says T&E
12:52 The Port Authority of Valencia launches the ZAL project in the Port of Valencia
12:11 Clarkson Port Services and Peak Group collaborate to deliver Port Agency services across the North Sea
11:42 Wan Hai Lines holds ship naming ceremony for new vessels
11:24 Consolidated shipping lines EBIT loss was $1.44 billion in Q4 2023: Sea-Intelligence
10:49 Seaspan Shipyards receives long-term contracts for the pre-construction work of the the Canadian Coast Guard's first six multi-mission vessels
10:14 Woodside completes sale of 10% scarborough interest

2024 March 26

18:02 COSCO Shipping Lines introduces new Americas service
17:30 Davie awarded first contract for design of icebreaker fleet under Canada’s National Shipbuilding Strategy
17:04 Sanctions complicate Arctic LNG ship sales, Hanwha Ocean says - Bloomberg
16:57 Terntank places an order for 1+1 additional wind/ methanol-ready hybrid tanker
16:28 BW LNG completes acquisition of two TFDE vessels from Stena Bulk
15:50 Hanwha Ocean develops VR-based special vehicle simulator
15:20 TotalEnergies and SINOPEC join forces to produce sustainable jet fuel at a SINOPEC's refinery
14:52 Wärtsilä Lifecycle Agreement to guarantee operational reliability of new wind farm installation vessel
14:23 Hudong-Zhonghua launches two LNG carriers
13:51 Cargo ship hits Baltimore’s Key Bridge
13:12 Final sanctioned tanker with Russian Sokol oil to reach China port - Reuters
12:42 Adani Ports acquires 95% of Odisha's Gopalpur Port from SP Group for $162 million
12:21 IHI and Yara Clean Ammonia agree to jointly assess clean ammonia business collaboration
11:41 Yara Clean Ammonia and Azane granted safety permit to build world's first low emission ammonia bunkering terminal
11:16 Wartsila and Royal Caribbean Group celebrate 15 years of collaboration on digital transformation
10:46 A global carbon tax on shipping is coming, says ABS Chairman and CEO
10:21 Eni, Fincantieri and RINA establish partnership for maritime transport decarbonization

2024 March 25

18:07 The Maritime and Port Authority of Singapore continues to investigate reports of oil spills off the port of Tuas
17:31 “K” Line, NIPPON HAKUYO and OPT Gate sign an agreement for a new fire detection system for car carriers
17:07 Greek merchant fleet recorded slight decline in January 2024
16:47 Hanwha Ocean Plans to develop green technology and naval ships
16:25 U-Ming Singapore and ITOCHU sign milestone MoU for the joint development of ammonia dual-fuel and de-carbonized vessels
15:34 Svitzer targets methanol-fuelled MAN 175DF-M engine for tug application
15:04 Wallenius Wilhelmsen signs contracts for four 9,300 CEU vessels with China Merchants Jinling Shipyard
14:40 Taiwan International Port to upgrade terminal facility at Kaohsiung
13:59 Сruise ship Carnival Freedom catches fire near Bahamas
12:59 Hanwha Ocean wins 2.4 tln-won order for 8 LNG ships
11:16 Inland Ports meet in Paris to talk about the innovation potential of inland ports
10:50 IMO agrees possible outline for maritime “net-zero framework”
10:24 Hapag-Lloyd to continue to avoid the Red Sea route
09:58 QatarEnergy enters time charter agreements with Nakilat for the operation of 25 LNG vessels

2024 March 24

16:18 Inchgreen Marine Park upgraded as part of £11m investment
15:14 A ribbon-cutting ceremony for Solent Rail Terminal Rail was held at the Port of Southampton
14:08 ESNA and Strategic Marine join forces to offer Surface Effect Ship (“SES”) Crew Transfer Vessels (“CTV”) to the market
13:07 First LNG powered vessel calls at HIP
12:49 Inter-array cable installation completed at Neart na Gaoithe offshore wind farm
11:32 Equinor ASA posts net income at USD 11.9 billion in 2023
09:25 Edda Wind announces the sale of Edda Passat