2018 December 18
Aleksey Likhachev, General Director, Rosatom Corporation
On construction of nuclear-powered icebreakers
- We have prepared a revised schedule approved by the Ministry of Industry and Trade on construction of the lead multipurpose icebreaker, the first and the second serial ones with the delivery in 2019, 2020 and 2021 accordingly.
They are supposed to be enough for current volumes of shipping in the Northern Sea Route (through 2022). To reach the target of 80 million tonnes by 2024 the decision (RF Government’s decision - Ed.) on construction of the third and the fourth serial icebreakers is also under implementation. Interdepartmental consultations have been held. We have determined the cost and the implementation period with the delivery scheduled for 2024. The third and the fourth serial icebreakers are to be delivered in 2026 (end of 2025).
This project (the third and the fourth serial ships) is being implemented with considerable commercial financing involved. The draft budget foresees required resources. As far as I know, the Ministry of Economic Development has already proposed inclusion of the third and the fourth serial icebreakers in the comprehensive plan of transport infrastructure development.
The traffic of 80 million tonnes and round-the-year shipping on the Northern Sea Route will encourage deployment of four mid-power icebreakers by 2024. The will start operation in the Gulf of Ob, in the western seas. More powerful icebreakers, the Yamal and the 50 Let Pobedy, as well as new multipurpose icebreakers can be involved on eastern routes, in heavy ice of East Siberian Sea.
Yet, the capacity will be limited and we will deploy the Leader icebreaker by 2027. The decision on its construction and budget financing has already been made. The ship will be built by Zvezda shipyard.
By 2024, we should have not two but four mid-power icebreakers. I would like to emphasize that their financing is full commercial, without involving budget resources. Together with the Ministry of Industry and Trade we should select shipyards able to meet the deadline. It is crucial for us because the financing is commercial and any delay presents a risk for investment projects and for financial indicators of the state corporation. In this respect we … are ready provide every assistance to the Ministry of Industry and Trade.
We understand that the lead Leader icebreaker should be followed by serial ones. The time of their introduction depends significantly on the growth of eastwards shipping after 2025 rather than on forecasts.
Transcript from the Government meeting on the Arctic development issues.
-
2019 January 14
Alexey Likhachev, CEO of the State Atomic Energy Corporation ROSATOM
On the Northern Sea Route and Arctic development plans
-
2019 March 7
Yury Trutnev, Presidential Plenipotentiary Envoy to the Far Eastern Federal District
On challenges of transport infrastructure development in the Arctic and on privileges for investors
-
2019 February 7
On Arctic development issues
-
2017 November 17
On providing RF-flagged ships with exclusive right to transport and store hydrocarbons in NSR waters
-
-
2021 January 22
https://www.dredgingtoday.com
Another dredger joins Astrakhan branch fleet
Due to the reception of these vessels, the dredging fleet of the Astrakhan branch increased up to 6 vesselsAnother dredger joins Astrakhan branch fleet
-
2021 January 22
https://www.offshore-energy.biz
SCF inks LNG newbuild charter deal with Total
The two companies have concluded a time charter agreement for up to 7 years for a newbuilding 174,000-cbm LNG carrierSCF inks LNG newbuild charter deal with Total
-
2021 January 22
https://www.ship-technology.com
Zvezda commences construction of second ARC7 LNG carrier
The LNG carriers are being constructed on behalf of gas industry company PAO NOVATEK for Arctic LNG2 ProjectZvezda commences construction of second ARC7 LNG carrier
-
2021 January 20
http://www.scf-group.com/
SCF further expands transit window through the Eastern part of the Russian Arctic
SCF’s LNG carrier Christophe De Margerie, reached Cape Dezhnev in Russia’s Far East, completing her eastbound voyage carrying a cargo of LNG along the Northern Sea RouteSCF further expands transit window through the Eastern part of the Russian Arctic
-
2021 January 20
https://www.nytimes.com
U.S. to Impose Sanctions on Ship Involved in Russian Gas Pipeline
The sanctions, which are to take effect on Tuesday, are the first action the United States has taken against the project, which has been a point of friction between Washington and Berlin...U.S. to Impose Sanctions on Ship Involved in Russian Gas Pipeline
-
2021 January 19
https://newsroom.portofantwerp.com/
Record container throughput limits losses in 2020, the year of coronavirus
The total throughput of Port of Antwerp in 2020 amounted to 231 million metric tonnes of cargo, a fall of 3.1% compared with the previous year. Thanks to the buoyant container throughput rates, which set a new record, the port was able to limit the overall decline in throughput. Compared with most...Record container throughput limits losses in 2020, the year of coronavirus