    GAO: Lead ship testing and reliability shortfalls will limit initial fleet capabilities

    The Navy faces technical, design, and construction challenges to completing Gerald R. Ford (CVN 78) that have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time, the U.S. Government Accountability Office (GAO) said in a press release.

    The Navy has achieved mixed progress to date developing CVN 78's critical technologies, such as a system intended to more effectively launch aircraft from the ship. In an effort to meet required installation dates aboard CVN 78, the Navy has elected to produce some of these systems prior to demonstrating their maturity--a strategy that GAO's previous work has shown introduces risk of late and costly design changes and rework, and leaves little margin to incorporate additional weight growth in the ship.
    In addition, progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges, and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008--to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.

    The Navy's strategy for providing timely demonstration of CVN 78 capabilities is hampered by post-delivery test plan deficiencies, Joint Strike Fighter aircraft delays, and reliability shortfalls affecting key ship systems. Additional risk is introduced due to the Navy's plan to conduct integration testing of key systems with the ship at the same time as initial operational test and evaluation (IOT&E). This strategy will constrain opportunities to implement timely, corrective actions if problems are discovered with key ship systems. In addition, significant discoveries during IOT&E could delay demonstration of ship capabilities. The Joint Strike Fighter, intended to operate with the carrier, has faced delays, and there is the likelihood of costly retrofits to the ship to accommodate the aircraft after CVN 78 is delivered to the Navy. But even after the ship commissions, several key ship systems will continue to face significant reliability shortfalls that will likely increase costs to the government and limit the ship's mission effectiveness. The extent of these limitations will not be known until after IOT&E. GAO contemplated making a recommendation to delay CVN 78 commissioning until the ship successfully completes IOT&E. However, based on additional information provided by DOD, GAO decided not to include this recommendation in the report.

    The Navy and shipbuilder are implementing process improvements aimed at reducing the cost of the follow-on ship, John F. Kennedy (CVN 79), ahead of the main construction contract award for that ship, currently planned for September 2013. CVN 79 is to be of nearly identical design to CVN 78. The shipbuilder plans to employ a new, more efficient build strategy, but remaining technical and design risks with the lead ship could interfere with the Navy's ability to achieve its desired cost savings for CVN 79. These uncertainties also affect the soundness of the Navy's current CVN 79 cost estimate, which is optimistic. These factors, when coupled with the existing sole source environment for aircraft carrier construction, may compromise the government's negotiating position for CVN 79.

    The Navy plans to spend over $43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines (1) technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates; (2) the Navy's test strategy for demonstrating CVN 78's required capabilities; and (3) actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense (DOD) and contractor officials.

    GAO recommends the Secretary of Defense take several actions aimed at ensuring Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, including conducting a cost-benefit analysis of required capabilities and associated costs. GAO is also recommending actions to improve the Navy’s knowledge about CVN 79 capabilities and costs before beginning contract negotiations. DOD concurred with one recommendation, partially concurred with three others, and did not concur with the recommendation to defer CVN 79’s detail design and construction contract award. GAO maintains that DOD’s current schedule for awarding this contract undermines the government’s negotiating position.


2024 May 6

18:00 CMA CGM to suspend Bremerhaven call on its SAFRAN service connecting East Coast South America with Europe
17:12 CMA CGM announces PSS from Asia to East Africa, South Africa and Indian ocean
16:47 Taylor Smith Shipyard announces cooperation agreement with Nouum Engineering
16:09 Incat Crowther-commissioned to design new fast supply vessel for African offshore energy sector
15:47 Seaspan completes rollout of Starlink across entire fleet
15:26 Asia is the largest importer of LNG
13:50 Goa shipyard holds the keel laying ceremony of the first new generation maritime patrol ship
13:20 Maersk says Red Sea disruption will cut capacity by 15-20% in Q2 2024
12:43 DP World acquires Laos dry port operator Savan Logistics
11:42 Seatrium secures FPSO topsides integration contract with MODEC
11:25 CMA CGM to strengthen and reshuffle its Africa lines - India Middle East Gulf services
10:46 Fortescue completes trials chassis and maneuverability testing of dual-fuelled ammonia-powered vessel in the Port of Singapore

2024 May 5

17:41 Visayas Container Terminal delivers enhanced productivity, efficiency to ICPC
15:07 Höegh LNG announces agreement to deploy FSRU Hoegh Galleon to Egypt
14:22 Metal Shark building 22 high-speed surface interceptor vessels for JDF
12:14 AAL's B-Class heavy lift ship named at a Chinese shipyard
10:04 DNV: April sees jump in methanol-fueled tanker orders

2024 May 4

15:17 Lomar takes bulker investment to $127 million inside a year
13:47 HD Hyundai, ABS to set standards for e-propulsion ships
12:08 Australian Govt selects BAE Systems and ASC to build sovereign nuclear powered submarines
10:51 Van Oord’s heavy lift installation vessel undergoes upgrade

2024 May 3

18:00 Holland America Line begins pilot test of renewable fuels on its flagship, Rotterdam
17:20 European Hydrogen Bank auction provides €720 million for renewable hydrogen production in Europe
17:06 GTT and PipeChina Innovation sign a License Agreement for the use of GTT membrane containment technology for onshore LNG storage
16:43 CMA CGM to launch M2X - Mexico Express Service connecting Far East to Mexico
16:31 Wartsila to supply the engines for a new Canadian Coast Guard Polar Icebreaker
15:58 The Port of Long Beach celebrates “Tri-gen” system for producing renewable hydrogen, electricity and water
15:06 Astrakhan region ports’ cargo volume in Q1, 2024 soars 78%
14:32 Valenciaport participates in a European project to promote the use of renewable energy for self-consumption in the port
13:50 Seatrade reaches settlement with Dutch Public Prosecution Service
13:15 Dennis Tetzlaff appointed Chief Operating Officer Fleet at Stena Line
12:40 ONE releases financial result for FY2023
12:20 IMO biofouling project to address biodiversity threat extended
11:30 Corvus Energy to supply ESS for the first net zero subsea construction vessel
11:10 Damen launches fully electric RSD-E Tug 2513 for Port of Antwerp-Bruges
10:30 Port of Rotterdam reduces CO2 emissions by 10% in 2023
10:02 HD KSOE wins $286mn order for four MGCs
10:00 Russian seaports in Q1, 2024: Infographics and Analytics
09:00 HD Hyundai Heavy secures contract to build LNG carrier duo

2024 May 2

18:07 World’s most environmentally friendly tug fleet delivered to HaiSea Marine
17:38 SOHAR Port and Freezone sings agreement with METCORE for Mass Flow Meter Implementation
17:23 Unifeeder launches China Gulf Express
16:59 Allseas receives T&I contract for Gennaker offshore wind farm
16:30 CMA CGM’s newest container vessel visited the HHLA TK Estonia terminal
15:46 DP World introduces new rail route from China to Turkey
14:32 Hybrid technology to optimise energy use and cut emissions for Matson Navigation Company’s new LNG-powered container ships
13:54 Bureau Veritas awards AiP for TotalEnergies’ Skipe V2 tool
13:24 Hapag-Lloyd launches first dry container tracking product “Live Position”
12:58 Europe’s ports have €80 billion investment needs for the next 10 years
12:15 MABUX: Bunker Outlook, Week 18, 2024
11:42 APSEZ FY24 net profit jumps 50%
11:19 Tristar Eships to manage its carbon footprint with Wartsila’s Decarbonisation Services
10:48 Topsoe awarded contract to support FEED study for new low-carbon ammonia plant in Louisiana, US
09:26 Maersk posts Q1 2024 results

2024 May 1

17:13 Matson picks Kongsberg Maritime's hybrid technology for its new LNG-powered container ships
16:22 All American Marine delivers hydrofoil-assisted tour vessel to Phillips Glaciers
15:24 Corvus Energy to supply ESS for the first Net Zero Subsea Construction Vessel
14:02 Stena Line taps Dennis Tetzlaff as Chief Operating Officer Fleet
12:31 APSEZ secures AAA Rating – India’s first private infrastructure developer with AAA
11:57 Unifeeder continues its expansion in Latin America
10:09 IMO's Legal Committee finalizes new guidelines on seafarer criminalization

2024 April 30

16:14 LR grants AiP to H2SITE’s AMMONIA to H2POWER technology
15:17 IRS partners with MARIN to enhance technical expertise in shipbuilding
13:42 Allseas T&I contract for Gennaker offshore wind farm
12:03 CSSC and QatarEnergy sign agreement for construction of 18 Q-Max class LNG carriers
10:13 First ship departs Baltimore through limited access channel

2024 April 29

17:42 Abu Dhabi leaps a staggering 10 places in 2024 LMC Report
16:19 Norwegian engine builder Bergen Engines joins FME MarTrans initiative
15:13 Hitachi, Chantiers de l’Atlantique to seal French offshore substation contract
14:53 Port of Greenock given vote of confidence with new Türkiye container service