    Hamburg port says arrivals delay caused congestion at container terminals

    In 2013 and the first few months of 2014, increasing ship sizes and the associated rise in throughput for container mega-ships resulted in increased levels of fluctuation in capacity utilisation (peaks) at Hamburg’s container terminals, the Port of Hamburg said in a press release.

    In addition, since early 2014 an unusual scenario has occured which many other European and Asian ports are also struggling with: a series of storms have resulted in ships arriving at the port partially with several day long delays. As a consequence the large volumes of export containers have accumulated, as they are delivered even if the vessels for their transportation have not yet arrived. This has caused the average dwell time for a container to double over the last few months. Up to 25 % of the overall storage capacity for exports is thus unavailable.

    Container stores are fully productive at a level of capacity utilisation of up to 80 %. In many places, capacity utilisation is currently up from its normal level of 75 % to almost 100 %. This increase means that not all of the terminals’ processes are functioning at normal levels of productivity. Due to this overload, the data processing system is not always able to select the optimal slot and it is necessary to utilise the maximum stacking height in the yards. This considerably increases the distance the transport equipment has to cover. A lot more restowing is necessary than normal, which is a time-consuming process. All of this costs productivity.

    With the already usually high levels of seaborne productivity, the container yard is in any case the bottleneck at the terminals. The unusually high increase in storage capacity utilisation is therefore noticeable throughout the system. As a result, loading and discharging of truck and rail transportation has recently failed to maintain its normal high level of quality.

    In addition, an extremely high volume of trucks calls at the terminals between 1 and 5 p.m. We have been unable to satisfactorily determine why so many trucks all arrive at the terminals during this period.

    The terminal operators have only very limited control over the containers’ long dwell times. Nonetheless, they have already implemented measures to maintain the individual terminals’ productivity: Additional yards have been established at some terminals in order to increase storage capacities. Additional equipment is used here.

    It is not currently foreseeable when the delays in ship arrivals and the resulting bottlenecks at the terminals will be eliminated. Accordingly, waiting times for truck services especially at peak times – from Monday to Friday – still cannot be ruled out. To ease this situation, short-term measures such as improved coordination with truckers are necessary. Forwarders and truckers are urgently invited to also operate in the evenings and at night as well as weekends whenever possible. Sufficient handling capacities without waiting periods are still available at these times.

    In the medium term a truck appointment system (slot system) should be set up, along the lines of the system already in operation for the dock railway. A further possibility are additional empty container areas in the immediate proximity of the terminals in order to reduce the volume of truck-based transshipment within the port. Removal of the ban on use of trucks on Sundays for transshipment within the port would further improve the situation.


2024 May 6

16:09 Incat Crowther-commissioned to design new fast supply vessel for African offshore energy sector
15:47 Seaspan completes rollout of Starlink across entire fleet
15:26 Asia is the largest importer of LNG
13:50 Goa shipyard holds the keel laying ceremony of the first new generation maritime patrol ship
13:20 Maersk says Red Sea disruption will cut capacity by 15-20% in Q2 2024
12:43 DP World acquires Laos dry port operator Savan Logistics
11:42 Seatrium secures FPSO topsides integration contract with MODEC
11:25 CMA CGM to strengthen and reshuffle its Africa lines - India Middle East Gulf services
10:46 Fortescue completes trials chassis and maneuverability testing of dual-fuelled ammonia-powered vessel in the Port of Singapore

2024 May 5

17:41 Visayas Container Terminal delivers enhanced productivity, efficiency to ICPC
15:07 Höegh LNG announces agreement to deploy FSRU Hoegh Galleon to Egypt
14:22 Metal Shark building 22 high-speed surface interceptor vessels for JDF
12:14 AAL's B-Class heavy lift ship named at a Chinese shipyard
10:04 DNV: April sees jump in methanol-fueled tanker orders

2024 May 4

15:17 Lomar takes bulker investment to $127 million inside a year
13:47 HD Hyundai, ABS to set standards for e-propulsion ships
12:08 Australian Govt selects BAE Systems and ASC to build sovereign nuclear powered submarines
10:51 Van Oord’s heavy lift installation vessel undergoes upgrade

2024 May 3

18:00 Holland America Line begins pilot test of renewable fuels on its flagship, Rotterdam
17:20 European Hydrogen Bank auction provides €720 million for renewable hydrogen production in Europe
17:06 GTT and PipeChina Innovation sign a License Agreement for the use of GTT membrane containment technology for onshore LNG storage
16:43 CMA CGM to launch M2X - Mexico Express Service connecting Far East to Mexico
16:31 Wartsila to supply the engines for a new Canadian Coast Guard Polar Icebreaker
15:58 The Port of Long Beach celebrates “Tri-gen” system for producing renewable hydrogen, electricity and water
15:06 Astrakhan region ports’ cargo volume in Q1, 2024 soars 78%
14:32 Valenciaport participates in a European project to promote the use of renewable energy for self-consumption in the port
13:50 Seatrade reaches settlement with Dutch Public Prosecution Service
13:15 Dennis Tetzlaff appointed Chief Operating Officer Fleet at Stena Line
12:40 ONE releases financial result for FY2023
12:20 IMO biofouling project to address biodiversity threat extended
11:30 Corvus Energy to supply ESS for the first net zero subsea construction vessel
11:10 Damen launches fully electric RSD-E Tug 2513 for Port of Antwerp-Bruges
10:30 Port of Rotterdam reduces CO2 emissions by 10% in 2023
10:02 HD KSOE wins $286mn order for four MGCs
10:00 Russian seaports in Q1, 2024: Infographics and Analytics
09:00 HD Hyundai Heavy secures contract to build LNG carrier duo

2024 May 2

18:07 World’s most environmentally friendly tug fleet delivered to HaiSea Marine
17:38 SOHAR Port and Freezone sings agreement with METCORE for Mass Flow Meter Implementation
17:23 Unifeeder launches China Gulf Express
16:59 Allseas receives T&I contract for Gennaker offshore wind farm
16:30 CMA CGM’s newest container vessel visited the HHLA TK Estonia terminal
15:46 DP World introduces new rail route from China to Turkey
14:32 Hybrid technology to optimise energy use and cut emissions for Matson Navigation Company’s new LNG-powered container ships
13:54 Bureau Veritas awards AiP for TotalEnergies’ Skipe V2 tool
13:24 Hapag-Lloyd launches first dry container tracking product “Live Position”
12:58 Europe’s ports have €80 billion investment needs for the next 10 years
12:15 MABUX: Bunker Outlook, Week 18, 2024
11:42 APSEZ FY24 net profit jumps 50%
11:19 Tristar Eships to manage its carbon footprint with Wartsila’s Decarbonisation Services
10:48 Topsoe awarded contract to support FEED study for new low-carbon ammonia plant in Louisiana, US
09:26 Maersk posts Q1 2024 results

2024 May 1

17:13 Matson picks Kongsberg Maritime's hybrid technology for its new LNG-powered container ships
16:22 All American Marine delivers hydrofoil-assisted tour vessel to Phillips Glaciers
15:24 Corvus Energy to supply ESS for the first Net Zero Subsea Construction Vessel
14:02 Stena Line taps Dennis Tetzlaff as Chief Operating Officer Fleet
12:31 APSEZ secures AAA Rating – India’s first private infrastructure developer with AAA
11:57 Unifeeder continues its expansion in Latin America
10:09 IMO's Legal Committee finalizes new guidelines on seafarer criminalization

2024 April 30

16:14 LR grants AiP to H2SITE’s AMMONIA to H2POWER technology
15:17 IRS partners with MARIN to enhance technical expertise in shipbuilding
13:42 Allseas T&I contract for Gennaker offshore wind farm
12:03 CSSC and QatarEnergy sign agreement for construction of 18 Q-Max class LNG carriers
10:13 First ship departs Baltimore through limited access channel

2024 April 29

17:42 Abu Dhabi leaps a staggering 10 places in 2024 LMC Report
16:19 Norwegian engine builder Bergen Engines joins FME MarTrans initiative
15:13 Hitachi, Chantiers de l’Atlantique to seal French offshore substation contract
14:53 Port of Greenock given vote of confidence with new Türkiye container service
14:09 Aker Solutions ASA:announces first quarter results 2024
13:37 Gasum Group's Q1 sales volumes rose 73% due to higher natural gas volumes
12:14 New Zealand cruise market on track for recovery