• 2012 April 5 09:54

    New Panama locks opening faces three-month delay

    The Panama Canal’s new locks will probably not be ready for their scheduled opening in October 2014, but will be ready for a trial run by a vessel in December, said Jorge Quijano, the engineer in charge of building the canal’s third set of locks, Journal of Commerce reports. The change in the opening date of the new locks is caused by the inability of the consortium that is building the new locks, Grupo Unidos por el Canal, to meet its contractual requirements for the concrete mix for the locks, which delayed the laying of the concrete from January until July of last year. The concrete has to last at least 100 years, but GUPC could not make concrete that met that standard until the canal authority brought in an outside expert to show them how to make it.

    The Panama Canal Authority received a letter Tuesday from GUPC with a new schedule for completing the work specified in its $3.2 billion contract for the locks. The schedule indicated that it will not be able to complete all the work required by its contract until April 2015, six months behind the target date for the opening of the new locks in October 2014. But the new schedule includes work on such elements as parking lots and building that are not essential to the new locks, said Quijano, who will become the canal authority’s new administrator on Sept. 4, succeeding Alberto Aleman Zubieta.

    Most industry observers had not expected the new locks to be in full commercial operation until 2015, but the three-month postponement of the target date for their opening is necessarily a disappointment for Zubieta, who has been saying all along that the locks would be ready in October 2014.

    They will be ready for testing in October, but not for full operation. “The pre-commissioning tests of the locks will actually start taking place in February 2014, so that says that by that time the lock structure is complete,” Quijano said. This is a three-month delay from the previous scheduled date for lock completion of December 2013. Construction consortium sends Panama Canal Authority new schedule for completion

    Starting in February 2014, the canal authority will test the gates and all of their electro-mechanical capabilities. The flooding of the locks is now scheduled for Sept. 15. “After that we will begin testing with water, which can take up to three months,” Quijano said. “Those are the tests that determine whether we take money out of the payment (to GUPC).”

    The canal authority has some leverage to make sure the locks are completed on schedule. Under its contract with the canal authority, GUPC faces contractual penalties of $300,000 per day if it cannot complete the locks on time, up to a maximum of $54 million. The GUPC consortium consists of Sacyr Vallehermoso of Spain, Impregilo of Italy, Jan De Nul of Luxembourg, and Constructora Urbana of Panama, which is known as CUSA.

    In addition to penalties for not completing the locks on time, Quijano said, GUPC could also face penalties of up to $200 million if the locks fail to meet two tests. The first test involves the time needed for water to rise to the required levels, which is supposed to take either 10 or 17 minutes, depending on whether or not it uses the water-saving basins. “For every minute they don’t meet that we start deducting up to $100 million,” he said.

    The second test involves the movement of the lock gates, which are supposed to be able to open and close within four and five minutes. “For every minute beyond five minutes, we start deducting up to $100 million.”

2024 May 1

17:13 Matson picks Kongsberg Maritime's hybrid technology for its new LNG-powered container ships
16:22 All American Marine delivers hydrofoil-assisted tour vessel to Phillips Glaciers
15:24 Corvus Energy to supply ESS for the first Net Zero Subsea Construction Vessel
14:02 Stena Line taps Dennis Tetzlaff as Chief Operating Officer Fleet
12:31 APSEZ secures AAA Rating – India’s first private infrastructure developer with AAA
11:57 Unifeeder continues its expansion in Latin America
10:09 IMO's Legal Committee finalizes new guidelines on seafarer criminalization

2024 April 30

16:14 LR grants AiP to H2SITE’s AMMONIA to H2POWER technology
15:17 IRS partners with MARIN to enhance technical expertise in shipbuilding
13:42 Allseas T&I contract for Gennaker offshore wind farm
12:03 CSSC and QatarEnergy sign agreement for construction of 18 Q-Max class LNG carriers
10:13 First ship departs Baltimore through limited access channel

2024 April 29

17:42 Abu Dhabi leaps a staggering 10 places in 2024 LMC Report
16:19 Norwegian engine builder Bergen Engines joins FME MarTrans initiative
15:13 Hitachi, Chantiers de l’Atlantique to seal French offshore substation contract
14:53 Port of Greenock given vote of confidence with new Türkiye container service
14:09 Aker Solutions ASA:announces first quarter results 2024
13:37 Gasum Group's Q1 sales volumes rose 73% due to higher natural gas volumes
12:14 New Zealand cruise market on track for recovery
11:40 Vitol announces satisfaction of a condition precedent relating to the golden power proceeding
10:41 JERA Energy India begins operations as JERA’s base of operations in the country

2024 April 28

15:13 IACS publishes new recommendation for conducting commissioning testing of BWMS
14:11 Skanska set for South Brooklyn Marine Terminal Buildout (SBMT)
12:27 Philly Shipyard and HD Hyundai Heavy Industries sign MoU
12:03 Equinor to commence second tranche of the 2024 share buy-back programme
10:16 Gebrüder Weiss enlarges logistics center in Budapest
09:37 Opening of MARIN's Seven Oceans Simulator centre (SOSc) in the Netherlands slated for May 2024

2024 April 27

16:36 National Transportation Safety Board: Undetected flooding from a through-hull pipe led to capsizing of dredging vessel
15:49 Chantiers de l’Atlantique picks Brunvoll propulsion for the world’s largest sailing ships
14:31 US Navy announces first MCM MP embarked on USS Canberra
13:42 Interim president Michelle Kruger takes helm at Austal USA
12:17 DEME annnounces start of share buyback program
10:28 Ships with Korean-made LNG containment face key supply chain disruptions

2024 April 26

18:04 Seaspan celebrates 30 years of ship repair in Victoria
17:31 HMM enhances maritime safety with AI technology
17:13 Potential Strait of Hormuz closure threatens 21% of global LNG supply - Drewry
16:42 Van Oord christens two new hybrid water injection dredgers and an unmanned survey vessel in Rotterdam
15:57 CMA CGM announces FAK rates from Asia to North Europe
15:24 MOL announced delivery of LPG dual-fuel LPG/ammonia carrier Aquamarine Progress II
14:53 DP World and Asian Terminals launch new Tanza Barge Terminal in Cavite
14:23 MH Simonsen orders eight hybrid methanol dual-fuel tankers at China’s Jiangxi New Jiangzhou Shipbuilding
13:47 DP World and Malaysia’s Sabah Ports form a partnership to manage Sapangar Bay Container Port
13:22 SCHOTTEL to equip Guangzhou Port Group’s latest e-tug with two RudderPropellers type SRP 360
12:57 FESCO Group proposes a mechanism in favour of Russian logistics operators over their foreign competitors in domestic transport market
12:39 SSK shipyard launches the Project 14400 support ship Nikolai Kamov in the Nizhny Novgorod region
12:33 Six companies start a joint study for the establishment of an ammonia supply chain based in the Tomakomai area of Hokkaido
11:52 European shipowners welcome 40% production benchmark for clean shipping fuels in Europe
11:14 Greek shipowners leaders in the secondary market once again
10:08 MPCC secures ECA-covered sustainable financing for its dual-fuel methanol newbuildings
09:38 Romanian port of Constantza to receive a new oil products terminal

2024 April 25

18:07 MSC collaborates with GSBN to trial integrated safe transportation certification verification process
17:23 China launches construction of cutting-edge marine research vessel
17:06 CMA CGM and Bpifrance launch €200mln fund to decarbonize French maritime sector
16:46 Avenir LNG orders two 20,000 M3 LNG bunker delivery vessels
16:05 Port of Amsterdam revenues up to €190.4 million in 2023
15:46 OOCL launches Transpacific Latin Pacific 5 to offer express linkage between Asia and Mexico
15:23 MOL is 1st Japanese shipping company to raise funds through transition linked loan using performance-based interest subsidy system
14:53 Trident Energy enters the Republic of Congo with strategic deal
14:21 LNG-powered ship moored in Koper for the first time
13:38 MABUX: Bunker Outlook, Week 17, 2024
13:32 The Grimaldi Group's Great Abidjan delivered in South Korea
13:12 European Parliament updates trans-European transport network guidelines
12:40 ClassNK releases route correction factors calculation tool "WACDAS"
12:10 MOL and Gaz System enter into agreement on FSRU project in Gdansk, Poland
11:31 Wartsila Gas Solutions to supply cargo handling system for a new 12.5k LNG bunkering vessel for Scale Gas
11:09 Wartsila secures China’s largest-ever methanol newbuild order
10:42 Valencia port community increases waste recovery by 75%
10:22 Kongsberg completes factory acceptance testing of the first production long-range autonomous underwater vehicle system HUGIN Endurance
09:53 Vladimir Putin: The BAM carrying capacity to reach nearly 42 million tonnes in 2024
09:47 Hanwha Ocean reports an operating profit of $38.6 mln on a consolidated basis in January-March 2024