• 2013 September 9 10:19

    GAO: Lead ship testing and reliability shortfalls will limit initial fleet capabilities

    The Navy faces technical, design, and construction challenges to completing Gerald R. Ford (CVN 78) that have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time, the U.S. Government Accountability Office (GAO) said in a press release.

    The Navy has achieved mixed progress to date developing CVN 78's critical technologies, such as a system intended to more effectively launch aircraft from the ship. In an effort to meet required installation dates aboard CVN 78, the Navy has elected to produce some of these systems prior to demonstrating their maturity--a strategy that GAO's previous work has shown introduces risk of late and costly design changes and rework, and leaves little margin to incorporate additional weight growth in the ship.
    In addition, progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges, and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008--to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.

    The Navy's strategy for providing timely demonstration of CVN 78 capabilities is hampered by post-delivery test plan deficiencies, Joint Strike Fighter aircraft delays, and reliability shortfalls affecting key ship systems. Additional risk is introduced due to the Navy's plan to conduct integration testing of key systems with the ship at the same time as initial operational test and evaluation (IOT&E). This strategy will constrain opportunities to implement timely, corrective actions if problems are discovered with key ship systems. In addition, significant discoveries during IOT&E could delay demonstration of ship capabilities. The Joint Strike Fighter, intended to operate with the carrier, has faced delays, and there is the likelihood of costly retrofits to the ship to accommodate the aircraft after CVN 78 is delivered to the Navy. But even after the ship commissions, several key ship systems will continue to face significant reliability shortfalls that will likely increase costs to the government and limit the ship's mission effectiveness. The extent of these limitations will not be known until after IOT&E. GAO contemplated making a recommendation to delay CVN 78 commissioning until the ship successfully completes IOT&E. However, based on additional information provided by DOD, GAO decided not to include this recommendation in the report.

    The Navy and shipbuilder are implementing process improvements aimed at reducing the cost of the follow-on ship, John F. Kennedy (CVN 79), ahead of the main construction contract award for that ship, currently planned for September 2013. CVN 79 is to be of nearly identical design to CVN 78. The shipbuilder plans to employ a new, more efficient build strategy, but remaining technical and design risks with the lead ship could interfere with the Navy's ability to achieve its desired cost savings for CVN 79. These uncertainties also affect the soundness of the Navy's current CVN 79 cost estimate, which is optimistic. These factors, when coupled with the existing sole source environment for aircraft carrier construction, may compromise the government's negotiating position for CVN 79.

    The Navy plans to spend over $43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines (1) technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates; (2) the Navy's test strategy for demonstrating CVN 78's required capabilities; and (3) actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense (DOD) and contractor officials.

    GAO recommends the Secretary of Defense take several actions aimed at ensuring Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, including conducting a cost-benefit analysis of required capabilities and associated costs. GAO is also recommending actions to improve the Navy’s knowledge about CVN 79 capabilities and costs before beginning contract negotiations. DOD concurred with one recommendation, partially concurred with three others, and did not concur with the recommendation to defer CVN 79’s detail design and construction contract award. GAO maintains that DOD’s current schedule for awarding this contract undermines the government’s negotiating position.


2024 May 19

12:44 New Pipeline Transition Alliance to focus on re-purposing natural gas infrastructure to hydrogen service
11:29 Yantai CIMC Raffles Offshore Ltd. shipyard launches dual-fuel offshore installation vessel for Van Oord
11:23 Major Scottish export terminal invests £750,000 to boost refrigerated cargo capabilities
10:12 Jan De Nul orders new XL cable-laying vessel

2024 May 18

15:24 SNAM's Q1 total revenues declined 1.9% to 895 million euros
14:17 KOTUG Int'l successfully pilots Tug Drone technology
12:04 Austal USA names Mark Santamaria as CFO
11:36 Silver Ships delivers four of seven coastal fast response boats
09:51 CMA CGM posts revenue of 11.8 billion for Q1 2024

2024 May 17

18:10 Bunker fuel sales at the Middle Eastern hub of Fujairah drop on a monthly basis in April 2024
17:52 Lloyd’s Register and Shandong Marine Group sign MoU
16:43 China reveals cooperation methods to protect and restore the Yangtze River
16:03 APM Terminals Barcelona holds the commissioning of 17 Konecranes NSC 644 EHY hybrid straddle carriers
15:13 Marine fuel demand in Panama declined in April 2024
14:43 MITSUI E&S and PACECO commence commercial operations of world's first hydrogen fuel cell zero emission RTG crane at Port of Los Angeles
14:23 ILWU Canada agrees to delay serving 72-hour strike notice on employer DP World Canada
13:31 Barge hits a bridge in Texas, damaging the structure and causing an oil spill
13:10 Container shipping costs on EU-S. Korea route surge over 30 pct amid Red Sea crisis
12:43 DP World invests €130m in Romania
12:21 Astrakhan hosts Russia-Iran talks on shipping cooperation on International North-South corridor
11:41 Seatrium awarded repeat FPSO integration contract from SBM Offshore
11:04 Bureau Veritas report highlights the potential of carbon capture technologies and the development of carbon value chains for shipping
10:41 Electramar christened in Helsinki
10:07 IMO Secretary-General spotlights seafarer safety amidst ongoing Red Sea attacks and resurging piracy
09:58 MABUX: Bunker Outlook, Week 20, 2024

2024 May 16

18:11 Kongsberg and Torghatten to develop self-driving ferry service linking Trondheim and the Fosen peninsula
17:42 “K” Line сonducts first trial use of B100 biofuel for carbon-free operations on car carrier
16:35 Deltamarin and ECOLOG unveil LP LCO2 carrier design
15:40 Seadrill enters agreement to sell its Qatar jack-up fleet
15:24 Scan Global Logistics and Hapag-Lloyd enter into major biofuel agreement in a new Green Collaboration
14:48 Edison Chouest feeder fleet for U.S. offshore wind market to be built to ABS Class
14:03 The Australian Government announces a funding package of $7.1 billion for budgeted programs to be administered by ARENA
13:54 The share of the idle container vessel fleet was 0.9% in April - Sea-Intelligence
13:25 The European Commission grants PCI status to CO2 value chain project developed by MOL with partners
12:14 HHLA's revenue decreased by 0.3 percent to € 363.6 millions in Q1 2024
11:42 MOL and TotalEnergies sign time charter contracts for 2 newbuilding LPG-fueled LPG carriers
10:40 Kalmar and Uniport Livorno agree on new terminal tractor order to enhance reliability, safety and service quality at Italian terminal
10:04 AMSA collaborates on a trial providing more recycling options for visiting foreign ships
09:59 SunGas Renewables and C2X announce strategic partnership

2024 May 15

18:07 MOL holds naming ceremony for newbuilding LNG carrier Greenergy Ocean to serve China National Offshore Oil Corporation
17:30 ClassNK and StormGeo mark significant collaboration to advance maritime decarbonization
17:02 Newly certified methanol valves to improve dual-fuel shipbuilding
16:45 HD KSOE to lease Subic shipyard in Philippines
16:25 Eidsvaag receives two forage carrier vessels designed and equipped by Kongsberg Maritime
15:58 ADNOC delivers first ever bulk shipment of CCS-enabled certified low-carbon ammonia to Japan
15:35 World's 1st wind challenger-equipped coal carrier achieves fuel savings of 17%
14:57 LR to support the retrofit of two Stena Line ferries to methanol
13:52 Port of Los Angeles nets record $58 million for harbor maintenance
13:32 CMA CGM to launch MCX - West Coast Central America
12:51 Port of Long Beach cargo volumes up 14.4% in April
12:21 First Ro-Pax vessel receives DNV Silent notation following successful sea trials with Wartsila propellers
11:41 Hapag-Lloyd transport volumes increased by 6.8 percent to 3 million TEU in Q1 2024
11:10 Cavotec signs two-year service agreement with Port of Salalah
10:41 China overtakes Korea in global shipbuilding competitiveness
09:58 The ports of Rotterdam and Delft join the CLARION project

2024 May 14

18:02 ICTSI to invest in new Southern Luzon gateway
17:31 ACL, BG Freight Line and Peel Ports Group start container service between Ireland and North America
17:10 Port of Hamburg is the first port in Europe to offer shore power for both container and cruise ships
16:31 Port of Gothenburg launches the platform "Digital Port Call"
16:18 NS United, NSY, Imabari Shipbuilding and Japan Marine United Corporation sign MOU for the construction of Cape-size bulk carriers using dual methanol fuel
15:56 Port of Antwerp-Bruges launches the world's first methanol-powered tugboat
15:29 The Ports of Barcelona and Shanghai will work together on innovation and decarbonisation projects
13:55 AD Ports Group announces Q1 results
12:58 NYK, NBP, TSUNEISHI SHIPBUILDING and Drax sign MOU to develop ‘bioship’ technology and plans to construct the world’s first biomass-fuelled ship
11:30 Maris Fiducia team up with HAV Hydrogen, Norwegian Hydrogen and Ankerbeer for zero emission bulk shipping
11:05 ABS and HD Hyundai Group sign MOU to advance medium-voltage power systems on ships
10:43 Finnlines’ new freight-passenger Superstar-class vessel Finnsirius awarded by Shippax
10:23 Kongsberg Maritime to design and equip two new salmon farm forage carrier vessels for Norwegian coastal cargo carrier Eidsvaag AS
09:48 Yara International and Kongsberg Digital enter collaboration on digital twin technology

2024 May 13

18:00 Capital dredging commences for Lowestoft Eastern Energy Facility