    Optimarin highlights how to navigate the challenges of BWTS retrofits

    The proper planning with a trusted and reliable supplier onboard is essential to navigate technical, logistical and regulatory hurdles to achieve compliance, says Optimarin.

    As well as detailed planning, drydock capacity must usually be secured ahead of time for a BWTS retrofit that typically has an engineering lead time of six months prior to installation. As an alternative, it is also possible to carry out the installation afloat if docking space is hard to come by.

    The first stage is to determine the right BWTS based on several selection criteria, including the size and type of vessel, classification, sailing pattern, flag state and port authority requirements, followed by procurement of the system.

    Then comes the planning stage that entails inspection and site engineering to look at structural, pipe, electrical and other elements, as well as carry out a 3D scan.

    This stage also includes design engineering to transfer site data to a digital platform, arrangement of structural plans for piping and outfitting, a bill of material and pre-fabrication drawings, with class approval required for the design.

    The final stage is installation and commissioning of the BWTS, followed by an initial survey of the operational system to verify compliance with class and regulatory requirements.

    Commissioning testing of a newly installed BWTS, which includes sampling and analysis of ballast water, is also required by the IMO to validate that the system functions according to performance standards. Such testing is now mandatory for all ships as of 1 June this year.

    This is necessary to gain an International Ballast Water Management Certificate that shows compliance with the IMO’s ballast water management convention set to enter into force in September 2024.

    But there are also logistical challenges with BWTS installation partly due to supply chain disruption caused by the Covid-19 pandemic and geopolitical issues that has affected delivery of system components, microchips and parts such as piping and cables.

    With its fast-track delivery model, Optimarin is able to deliver its flexible, modular BWTS in 6-10 weeks, and can access available drydock capacity at one of partner Newport Shipping’s global network of 15 affiliate yards.

    The modular design of the system makes it highly adaptable for installation on different vessel types and deck configurations with limited space.

    And the proven and reliable system can demonstrate documented compliance with the so-called D2 standard of viable organisms for ballast water discharges as stipulated by the IMO.




2024 March 28

17:35 Latvian port equipment manufacturer Bleste introduces new bulk handling ‘bucket’
17:05 Investors upgrade Navios Maritime Partners
16:25 DEME reports 22% increase in the orderbook and a record-high turnover of 3.3 billion euros in 2023
16:14 MABUX: Bunker Outlook, Week 13, 2024
15:41 AD Ports Group announced the opening of Saadiyat Marina & Ferry Terminal and Rabdan Marina
15:11 Sydney invests $11.5 million in two new operational vessels designed by Incat Crowther
14:55 China’s Jinzhao wins Peru $405m port construction contract
14:13 APM Terminals Moín handled six million TEU
13:48 ClassNK grants Innovation Endorsements for Products & Solutions to two innovative initiatives by MOL
13:37 Konecranes launches its flagship Konecranes X-series industrial crane
12:53 United European Car Carriers UECC spearheads collaboration with industry leaders to advance CNSL as a sustainable marine fuel
12:26 Ocean Network Express announces Transpacific service
11:48 Yang Ming announces 2025 Trans-Pacific service network
11:24 Fincantieri signs contract for the supply of two PPAs to Indonesia
10:42 Maersk transported more than 660,000 TEU using clean fuel in 2023
10:23 Documentation delays push industry costs to $3bn
09:48 PONANT and FARWIND Energy partner to develop green hydrogen refueling solutions

2024 March 27

18:22 Bureau Veritas awards world’s first prototype certification for SolarDuck’s floating offshore solar solution
17:58 The recently converted Allseas's shallow water pipelay barge starts preparations for its first commercial project
17:38 The Port of Rotterdam calls on the European Commission and Parliament to focus on actively promoting green energy
15:23 SEFE to become sole shareholder of WIGA
14:53 Ocean Installer secures yet another SLM contract with Equinor
14:23 Cadeler signs offshore wind turbine installation contract for the vessel Wind Scylla
13:42 Carnival Cruise Line orders 5th Excel-class cruise ship
13:11 Maersk and MSC overcharging cargo owners for EU ETS, says T&E
12:52 The Port Authority of Valencia launches the ZAL project in the Port of Valencia
12:11 Clarkson Port Services and Peak Group collaborate to deliver Port Agency services across the North Sea
11:42 Wan Hai Lines holds ship naming ceremony for new vessels
11:24 Consolidated shipping lines EBIT loss was $1.44 billion in Q4 2023: Sea-Intelligence
10:49 Seaspan Shipyards receives long-term contracts for the pre-construction work of the the Canadian Coast Guard's first six multi-mission vessels
10:14 Woodside completes sale of 10% scarborough interest

2024 March 26

18:02 COSCO Shipping Lines introduces new Americas service
17:30 Davie awarded first contract for design of icebreaker fleet under Canada’s National Shipbuilding Strategy
17:04 Sanctions complicate Arctic LNG ship sales, Hanwha Ocean says - Bloomberg
16:57 Terntank places an order for 1+1 additional wind/ methanol-ready hybrid tanker
16:28 BW LNG completes acquisition of two TFDE vessels from Stena Bulk
15:50 Hanwha Ocean develops VR-based special vehicle simulator
15:20 TotalEnergies and SINOPEC join forces to produce sustainable jet fuel at a SINOPEC's refinery
14:52 Wärtsilä Lifecycle Agreement to guarantee operational reliability of new wind farm installation vessel
14:23 Hudong-Zhonghua launches two LNG carriers
13:51 Cargo ship hits Baltimore’s Key Bridge
13:12 Final sanctioned tanker with Russian Sokol oil to reach China port - Reuters
12:42 Adani Ports acquires 95% of Odisha's Gopalpur Port from SP Group for $162 million
12:21 IHI and Yara Clean Ammonia agree to jointly assess clean ammonia business collaboration
11:41 Yara Clean Ammonia and Azane granted safety permit to build world's first low emission ammonia bunkering terminal
11:16 Wartsila and Royal Caribbean Group celebrate 15 years of collaboration on digital transformation
10:46 A global carbon tax on shipping is coming, says ABS Chairman and CEO
10:21 Eni, Fincantieri and RINA establish partnership for maritime transport decarbonization

2024 March 25

18:07 The Maritime and Port Authority of Singapore continues to investigate reports of oil spills off the port of Tuas
17:31 “K” Line, NIPPON HAKUYO and OPT Gate sign an agreement for a new fire detection system for car carriers
17:07 Greek merchant fleet recorded slight decline in January 2024
16:47 Hanwha Ocean Plans to develop green technology and naval ships
16:25 U-Ming Singapore and ITOCHU sign milestone MoU for the joint development of ammonia dual-fuel and de-carbonized vessels
15:34 Svitzer targets methanol-fuelled MAN 175DF-M engine for tug application
15:04 Wallenius Wilhelmsen signs contracts for four 9,300 CEU vessels with China Merchants Jinling Shipyard
14:40 Taiwan International Port to upgrade terminal facility at Kaohsiung
13:59 Сruise ship Carnival Freedom catches fire near Bahamas
12:59 Hanwha Ocean wins 2.4 tln-won order for 8 LNG ships
11:16 Inland Ports meet in Paris to talk about the innovation potential of inland ports
10:50 IMO agrees possible outline for maritime “net-zero framework”
10:24 Hapag-Lloyd to continue to avoid the Red Sea route
09:58 QatarEnergy enters time charter agreements with Nakilat for the operation of 25 LNG vessels

2024 March 24

16:18 Inchgreen Marine Park upgraded as part of £11m investment
15:14 A ribbon-cutting ceremony for Solent Rail Terminal Rail was held at the Port of Southampton
14:08 ESNA and Strategic Marine join forces to offer Surface Effect Ship (“SES”) Crew Transfer Vessels (“CTV”) to the market
13:07 First LNG powered vessel calls at HIP
12:49 Inter-array cable installation completed at Neart na Gaoithe offshore wind farm
11:32 Equinor ASA posts net income at USD 11.9 billion in 2023
09:25 Edda Wind announces the sale of Edda Passat

2024 March 23

17:19 Maersk opens new warehouse facility in Tijuana, Mexico for cross-border capabilities