The news source reported that eight new tandem-lift cranes and 20 rail-mounted gantry cranes (RMGs) have been delivered to the Jebel Ali terminal, increasing the total number of lift cranes to 16 and RMGs to 38.
Most of the new cranes have been commissioned and are operational, while the remaining are expected to commence operations shortly. Additional equipment is expected to be installed at the port in the coming months, according to Emirates Business.
The second phase of Container Terminal-2 at Jebel Ali is expected to have 29 tandem-lift cranes and 60 RMGs, when fully operational in the first quarter of 2009. The Container Terminal-2 is expected to have a total capacity in excess of five million 20-foot container units when fully operational.