1. Home
  2. Maritime industry news - PortNews
  3. Onezhsky Shipyard of FSUE Rosmorport completes first stage of repairs of Enisey pilot boat

2015 August 5   16:38

Onezhsky Shipyard of FSUE Rosmorport completes first stage of repairs of Enisey pilot boat

Onezhsky Shipyard has successfully completed the first stage of repairs of the Enisey pilot boat, which was put to the building berth in early June 2015, says press center of Rosmorport.

At present the hull construction and external shell of the boat have been inspected and repaired, electric mechanisms and equipment have been repaired. Steering mechanisms and shaft lines are being repaired. The boat is being prepared for painting.

Enisey has not been in operation since 2007. After the boat was transferred to the economic management of FSUE “Rosmorport”, it was technically inspected and inventoried, and a crew for the boat was formed. Enisey became the first vessel that Onezhsky Shipyard received after resuming its activities on 06 June 2015. When repairs are finished, the boat will go to Astrakhan Seaport and be used as a floating base for pilots.

Aside from repairing the Enisey boat, Onezhsky Shipyard is now constructing two buoy boats and three work boats.