As of today, 57.8 hectares of the territory has been cleared. Excavating including drilling and blasting amounted to 5.75 mln m3. Deepening of the water area – 118,460 m3. According to the plan the construction is to be completed in December. The construction is being carried out by three companies including Koksokhimmontazh CJSC and Inzhtransstroi CJSC.
A number of local organizations are involved in operations including Nakhodka Shiprepairing Plant, Transstroi LLC and Dalenergomontazh.
Introduction of the specialized sea oil-loading terminal in Kozmino Bay will create a new industry in Primorje – pipeline transportation of oil, which is to expand the taxable base of the Primorski Territory, the report reads.