  3. Van Oord starts cable installation at Iberdrola’s Baltic Eagle offshore wind farm

2023 October 4   17:03

Van Oord starts cable installation at Iberdrola’s Baltic Eagle offshore wind farm

After Van Oord’s heavy lift installation vessel Svanen completed installation of all fifty monopiles for Iberdrola Deutschland’s Baltic Eagle offshore wind farm, Van Oord now continues installing transition pieces and starts cable installation. This week the inter-array cable loading onto Van Oord’s cable-laying vessel Nexus has commenced, according to the company's release.

In total, Van Oord will install approximately 70 kilometres of 66kV inter-array cables, manufactured by subcontractor TKF. To protect the cables, Van Oord will deploy its trencher Dig-It later this year to bury them. This Tracked Remotely Operated Vehicle (TROV) drives unmanned over the seabed and creates a trench for the cables by liquefying the seabed.

To complete the foundations for the wind turbines, Van Oord is currently installing the transition pieces on the previously installed monopiles. The transition pieces were transported from the manufacturing yard in Aviles to the Van Oord storage facility in Mukran, Germany. At Van Oord’s facility the final preparations and equipment is installed to enable the installation.

The Baltic Eagle offshore wind farm is located 30 kilometres northeast of the German island of Rügen and covers a 40 square kilometre area. With a production capacity of 476 MW, Iberdrola’s Baltic Eagle offshore wind farm will deliver renewable energy to 475,000 households while reducing carbon dioxide emissions by approximately 800,000 tonnes annually. It is scheduled to be fully operational by the end of 2024. Van Oord is responsible for the transport and installation of the wind turbine foundations and the supply, transport and installation of the inter-array cables.