Investment will total US$300 million for the first phase until 2013, which will complete the main quay of 800m for mother ships, a barge quay of 260m and a yard space of 33ha. The annual capacity is 1.2 million TEUs.
The second phase is planned to finish in 2014 when the yard space will increase to 72ha and the main quay will expand to 1,150m, the barge quay to 370m. Its capacity will increase to 2.4 million TEUs.
The Cai Mep area, where around 70 percent of the country's container volume is concentrated, also includes several other smaller terminals.