    GAO: Lead ship testing and reliability shortfalls will limit initial fleet capabilities

    The Navy faces technical, design, and construction challenges to completing Gerald R. Ford (CVN 78) that have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time, the U.S. Government Accountability Office (GAO) said in a press release.

    The Navy has achieved mixed progress to date developing CVN 78's critical technologies, such as a system intended to more effectively launch aircraft from the ship. In an effort to meet required installation dates aboard CVN 78, the Navy has elected to produce some of these systems prior to demonstrating their maturity--a strategy that GAO's previous work has shown introduces risk of late and costly design changes and rework, and leaves little margin to incorporate additional weight growth in the ship.
    In addition, progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges, and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008--to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.

    The Navy's strategy for providing timely demonstration of CVN 78 capabilities is hampered by post-delivery test plan deficiencies, Joint Strike Fighter aircraft delays, and reliability shortfalls affecting key ship systems. Additional risk is introduced due to the Navy's plan to conduct integration testing of key systems with the ship at the same time as initial operational test and evaluation (IOT&E). This strategy will constrain opportunities to implement timely, corrective actions if problems are discovered with key ship systems. In addition, significant discoveries during IOT&E could delay demonstration of ship capabilities. The Joint Strike Fighter, intended to operate with the carrier, has faced delays, and there is the likelihood of costly retrofits to the ship to accommodate the aircraft after CVN 78 is delivered to the Navy. But even after the ship commissions, several key ship systems will continue to face significant reliability shortfalls that will likely increase costs to the government and limit the ship's mission effectiveness. The extent of these limitations will not be known until after IOT&E. GAO contemplated making a recommendation to delay CVN 78 commissioning until the ship successfully completes IOT&E. However, based on additional information provided by DOD, GAO decided not to include this recommendation in the report.

    The Navy and shipbuilder are implementing process improvements aimed at reducing the cost of the follow-on ship, John F. Kennedy (CVN 79), ahead of the main construction contract award for that ship, currently planned for September 2013. CVN 79 is to be of nearly identical design to CVN 78. The shipbuilder plans to employ a new, more efficient build strategy, but remaining technical and design risks with the lead ship could interfere with the Navy's ability to achieve its desired cost savings for CVN 79. These uncertainties also affect the soundness of the Navy's current CVN 79 cost estimate, which is optimistic. These factors, when coupled with the existing sole source environment for aircraft carrier construction, may compromise the government's negotiating position for CVN 79.

    The Navy plans to spend over $43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines (1) technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates; (2) the Navy's test strategy for demonstrating CVN 78's required capabilities; and (3) actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense (DOD) and contractor officials.

    GAO recommends the Secretary of Defense take several actions aimed at ensuring Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, including conducting a cost-benefit analysis of required capabilities and associated costs. GAO is also recommending actions to improve the Navy’s knowledge about CVN 79 capabilities and costs before beginning contract negotiations. DOD concurred with one recommendation, partially concurred with three others, and did not concur with the recommendation to defer CVN 79’s detail design and construction contract award. GAO maintains that DOD’s current schedule for awarding this contract undermines the government’s negotiating position.


2024 July 16

18:02 China extends visa-free transit policy to 37 ports
17:25 Works on schedule for the Ravenna regasifier, with the plant operational in the first quarter of 2025
17:05 STX Heavy Industries changes name to “HD Hyundai Marine Engine”
16:45 OOCL's revenue rises 14pc to US$2.2bln
16:20 Saltchuk acquires all of the outstanding shares of Overseas Shipholding Group
15:57 EU sets four conditions for the port of Piraeus inverstments
15:41 Serbia to open tender for Prahovo port overhaul in 2024
15:37 EIB lends €90 million for sustainable expansion of the Port of Livorno
15:34 Crew of capsized oil tanker off Oman still missing
15:14 Lomarlabs signs with Cargokite to develop a new ship class of micro ships
14:47 Greece extends naval drills that deter Russian oil transfers - Bloomberg
14:08 The Official Journal of the European Union publishes the first-ever EU regulation to reduce methane emissions
13:24 High cat fines found in the Amsterdam-Rotterdam-Antwerp region bunker fuel samples, alerts CTI-Maritec
12:58 Yangzijiang Shipbuilding works to acquire over 866,671 sqm of land for new clean energy ship manufacturing base
12:42 GTT entrusted by Samsung Heavy Industries with the tank design of a new FLNG
10:47 Maersk signs an MoU for ship recycling in Bahrain

2024 July 15

18:06 European Shipowners and Maritime Transport Unions launch initiative to support shipping and seafarers in the digital transition
17:35 APM Terminals Mumbai switches to 80% renewable electricity
17:05 Seaspan Shipyards welcomes the formation of the “ICE Pact”
16:41 World’s first entirely hydrogen-powered ferry welcomes passengers in San Francisco Bay
16:26 FMC issues request for additional information regarding Gemini Agreement
16:24 Saipem awarded two offshore projects in Saudi Arabia worth approximately 500 million USD
16:12 Pecém Complex selects Stolthaven Terminals and GES Consortium as H2V Hub green ammonia operator
15:43 Singapore's bunker sales rise 8.5% in the first half of 2024
15:27 TORM purchases eight and sells one second-hand MR vessel
14:55 Adani plans to build port in Vietnam
13:35 Regulator gives conditional nod to HD Korea Shipping's purchase of stake in STX Heavy
13:02 HD Korea Shipbuilding wins US$2.67 billion order to build 12 container carriers
12:51 Maersk introduces SH3 ocean service between China and Bangladesh
12:24 ABS to сlass two new Seatrium FPSOs for Petrobras
11:42 CSP Abu Dhabi Terminal surpasses throughput of 5 mln TEUs
11:11 Fincantieri launches the seventh PPA “Domenico Millelire” in Riva Trigoso
10:51 India's first transshipment port receives its first container ship
10:35 The “Egypt Green Hydrogen” project in SCZONE wins a contract worth € 397 million to export green fuel to Europe

2024 July 14

15:17 FMC issues request for additional information regarding Gemini agreement
13:06 Lummus and MOL Group begin engineering execution on advanced waste plastic recycling plant in Hungary
10:51 Chinese line launches new Arctic container service to Arkhangelsk
09:49 Malta PM tours Abela toured MSC World Europa officially inagurates Valletta shore power

2024 July 13

15:47 €11 million for 1-MW Dynamic Electrolyser Unit
14:11 PSA Group and Singapore mitigate impact of global supply chain disruptions
12:23 NREL: Offshore wind turbines offer path for clean hydrogen production
10:06 MMMCZCS releases a technical, environmental, and techno-economic analysis of the impacts of vessels preparation and conversion

2024 July 12

18:00 Qingdao Port International to buy oil terminal assets for $1.30 billion
17:36 Saipem signs framework agreement with bp for offshore activities in Azerbaijan
17:06 AG&P LNG and BK LNG Solution signs an agreement to bring BKLS's first LNG spot cargo into China
16:31 Allseas removes final Brent platform with historic lift
15:58 ZPMC Qidong Marine Engineering launches the world’s largest FPSO bow section for Petrobras
15:25 MSC acquires Gram Car Carriers
14:58 ABP boosts marine capability through pilot launch upgrades
14:34 Fincantieri receives ISO 31030 attestation from RINA
13:52 Second new dual-fuel fast Ro-Pax ferry to enter service for Balearia after successful sea trials
13:24 ADNOC deploys AIQ’s world-first RoboWell AI solution in offshore operations
12:59 ABS issues AIP for new gangway design from Pengrui and COSCO
11:38 Port of Long Beach data project receives $7.875 mln to speed goods delivery
11:15 ZeroNorth to provide its eBDN solution on 12 barges operated by Vitol Bunkers in Singapore
10:46 Seatrium secures customer contract agreement from Teekay Shipping for the repairs and upgrades of a fleet of vessels
10:14 Liquid Wind and Uniper enter into strategic partnership to accelerate the development of eFuels

2024 July 11

18:06 Yanmar and Amogy to explore ammonia-to-hydrogen integration for decarbonized marine power
17:36 COSCO Shipping receives first 7500 CEU LNG dual-fuel PCTC
17:06 Monjasa adds two tankers and targeting West Africa’s offshore industry
16:34 Biden administration announces funding for 15 small shipyards in 12 states
16:10 Iran's Ports and Maritime Organization attracts nearly $1.7bln of investment in ports, maritime sector
15:52 The added value of Chinese port cities up to US$869.05 bln in 2023
15:25 HD Hyundai becomes first Korean shipbuilder to sign MSRA with US Navy
13:41 NovaAlgoma orders the world’s largest cement carrier
13:21 Steerprop selected to provide comprehensive propulsion systems for world's largest cable-laying vessel
12:41 Integrated Wartsila propulsion package supports decarbonisation and efficiency goals for James Fisher tankers
12:36 MABUX: Bunker Outlook, Week 28, 2024
12:10 Valencia Port Authority signs an agreement with C.N.E. Hydrogen and Fuel Cells to promote hydrogen research
11:41 Long Beach, Los Angeles ports partner for zero-emissions future