TOTE Maritime Alaska is adjusting the LNG conversion schedule and has elected to delay the upcoming Midnight Sun LNG conversion phase-1 dry-dock by 1 year. Midnight Sun was originally scheduled to undergo phase 1 of the LNG conversion from mid-December 2018 through early-February 2019. TOTE Maritime Alaska will continue sailing both vessels throughout the year with the exception of routine holiday single-sailings.
The adjustment to the conversion schedule aligns the Orca’s LNG-readiness to the most recent timeline for Tacoma’s LNG-plant completion.
In place of this year’s dry dock period, our team will continue preparing Midnight Sun’s transition to LNG for items that don’t require a dry-dock.
TOTE Maritime Alaska is fully committed to convert the Orca class vessels to LNG, the most environmentally friendly maritime fuel available.
The new conversion schedule is as follows;
Midnight Sun Phase 1: 2019-2020
North Star Phase 2: 2020-2021
Midnight Sun Phase 2: 2021-2022
About Tote Maritime
TOTE Maritime, through its operations in Alaska and Puerto Rico, provides high-speed liner services in the U.S. domestic trade. TOTE Maritime provides twice-weekly and dedicated routes to Alaska, Puerto Rico and the U.S. Virgin Islands, connecting residents in these non-contiguous regions with the supplies they need to support their families, businesses and local economies.