Having built the body of the hydraulic works, the company is looking to complete the whole project in August.
By far, CNY 740 million has been invested in the project, compared with the plan of CNY 1.379 billion total investment.
After achieving completion, the wharf apron of the port can berth 100,000 to 300,000-ton very large crude carriers (VLCC) and have an annual handling capacity of 20 million tons, citing a report.