Production drilling started on Johan Sverdrup

At 00:00 on Tuesday 1 March the Deepsea Atlantic drilling rig commenced on the first of a total of 35 wells to be drilled in the first phase of the Johan Sverdrup field development.

The rig is drilling the first production well through a predrilling template that was installed on the field in the summer of 2015. A total of eight wells will be drilled through the predrilling template, before the rig is relocating to drill injection wells on three locations on the field.

In 2018 the permanent Johan Sverdrup drilling platform will be installed as the second of four platforms. The drilling platform is currently being constructed at Aibel’s yard in Haugesund, north of Stavanger, and in Thailand. When the drilling platform is installed and operational, the eight predrilled wells will be hooked up from the predrilling template. At this point Deepsea Atlantic will be drilling the injection wells providing reservoir pressure support to maintain high field production.

The operator Statoil, the rig owner Odfjell Drilling and the drilling service provider Baker Hughes have cooperated closely to ensure safe and cost-effective deliveries. The Johan Sverdrup project introduces integrated drilling services as a new concept, which means that Baker Hughes will provide the main deliveries together with Odfjell Drilling.

The contract for integrated drilling services worth NOK 1.5 billion was awarded to Baker Hughes on 6 July 2015.

The contract for rig and drilling services on Johan Sverdrup, totalling more than NOK 4.35 billion, was awarded to Odfjell Drilling on 15 June 2015.

Contracts worth more than NOK 50 billion have been awarded by the Johan Sverdrup project. More than 70% of them have been awarded to suppliers with a Norwegian billing address.