Statoil: three wells for the price of one
Old and partly lost slots that were given up as providers of new production triggered new solutions for Snorre B. The result was three wells with an average price of NOK 170 million, compared to NOK 490 as reference base.
Drilling & well (D&W) has recently delivered three new wells on the North Sea Snorre B field, contributing strongly to the corporate goal of «radical change» to reduce the breakeven for new wells.
The three wells, C-2, C-3 and C-4, have boosted Snorre B production by 30%.
“We estimate the price per barrel for these wells to be well below USD 10. Snorre B is currently producing around 80,000 barrels per day, which is a very satisfactory result. Together with D&W we have found the right drilling targets for our wells, and when we add a predictable and long-term drilling plan allowing optimisation and higher efficiency, we have the success factors,” says Oddmund Rismyhr, acting head of Snorre Petec.
New ideas – new possibilities
“This had not been the outcome if the slots had not been so bad at the outset, forcing us to be innovative. Due to a damaged C-3, for example, we applied a simplified casing design. This resulted in a short and quick well,” says Johan Dahl, head of D&W planning.
The cost reduction recipe involved a standardised and simplified well design – a standard completion design for all wells. The same type of drilling fluid was also applied to allow reuse. By carrying out the same operations in series they also saved a lot of time and resources, as they were able to complete all stages – drilling, lower completion, upper completion and Christmas tree setting – three times when they first started the operations.
“If we drill only one well, we must rent equipment and send it back to shore, while the remaining completion equipment and drilling fluid must be sent to shore when we are done. In this case we did the same operations three times, saving much time, improving use of resources and reducing costs and rental time. We also save a lot on mobilisation costs and logistics,” he says.
“At the same time we learn a lot from each well, which is reflected in the reduction in time spent on sub-operations during the process,” says Dahl.
Took advantage of the good weather season
The planning leader points out the good cooperation between D&W and Petec, which allowed them i.e. to include weather considerations in their planning. Normally they experience 35% waiting on weather during the months of the year with the most demanding weather conditions. Operations in bad weather often lead to major downtime incidents. This has been avoided and consequently they have succeeded at their first attempt.
“Earlier we wanted to start production immediately, and it was therefore not considered to adapt operations to the weather conditions. But we realise that when we make a good plan that takes this aspect into consideration and has a long-term perspective we achieve higher production sooner than we did before. If we had done like we did in the old days, we would not have been able to deliver more than two of these three wells, with the starting point we had at that time,” says Dahl.
Aiming for perfection
For the D&W community on Snorre there is only one reference base that matters.
“We are only looking at how close to a «perfect well» we can get,” says Ilhan Løwen, drilling superintendent of D&W.
This is the result of the best sub-operations completed in wells previously and combined in a fictitious reference well.
“We have made it a little difficult for ourselves by including reference wells from the field start-up all the way back in 2001,” he continues.
The «perfect well» time consumption for C-4, C-3 and C-2 was 49, 46 and 69 days respectively. The actual time consumption was 58, 58 and 91 days. The costs were NOK 168, 149 and 193 million. The average price in the period 2009–2013 was NOK 490 million.