  3. Swiber with JV partner completes floatover installation of central processing platform for NC - 3 Gas Field off Sarawak

2015 December 21   13:13

Swiber with JV partner completes floatover installation of central processing platform for NC - 3 Gas Field off Sarawak

Swiber Holdings Limited together with  its  Joint  Venture  partner Alam Maritim Sdn Bhd , Malaysia, has successfully completed its offshore installation scope of work  for the  NC3 Field, a part of the SK 316 Gas Development Project off Sarawak Malaysia, the company said in its press release.

The  NC 3 Field Development  EPCIC project for PETRONAS Carigali Sdn Bhd , Malaysia was  awarded to TMJV (Technip  – MMHE Joint Venture). TMJV subcontracted the Offshore T&I  (Transportation  and  Installation) scope to Alam Swiber Sdn Bhd.

The scope of work  was  divided into two campaigns. The first campaign involve d the  transportation and installation of a Wellhead Platform Jacket and Topside (WHP) , the launching  and installation of a 9,500mT  Central P rocess Platform  Jacket  ( CPP ) as well as the installation of  a  link Bridge between  the  CPP and WHP Platforms . The offshore installation for Campaign 1 was  successfully executed  in  between  March and May  2015. The second campaign  involved the installation by Float - Over  of  the 13,000m TCPP  Topside on  the previously installed  Jacket. It  was  executed  with in  a challenging  offshore  installation  schedule  from the  08 th to  the  13 th of  September  2015.

Actual mating of the topside  was performed in less than 4 hours on 12 th September 2015. For these  operations,  Swiber utilised its in - house vessels, mainly the  Derrick Lay Barge Swiber Kaizen 4000 , the Float - over and  Launch  Barges  Holmen Pacific and  Holmen Atlantic, as  well as an array of Offshore Support Vessels. 