1. Home
  2. Maritime industry news - PortNews
  3. Concrete works start at decking of berth No 6 in port Bronka (photo)

2014 April 10   15:39

Concrete works start at decking of berth No 6 in port Bronka (photo)

 

Concrete works have commenced at the decking of the berth No 6 (including the wing) of the Marine Multipurpose Complex Bronka (MMPK Bronka, Big Port St. Petersburg), says the project investor Fenix LLC. 

2,600 m3 of concrete is to be used at the berth intended for handling of container carriers. The work is to be completed in May 2014.

Total length of the berths at the start-up complex will make 1,430 m.

The Marine Multipurpose Complex Bronka (MMPK Bronka) is being built on the southern shore of the Gulf of Finland, in the place where the dam and the ring road border the territory of Lomonosov. The Bronka Complex will comprise three specialized facilities: a container terminal encompassing 107 hectares, Ro-Ro terminal of 57 ha and logistics center of 42 ha.  Container terminal will feature the 1.176 m-long waterfront (including 5 berths). The waterfront of rolling cargo terminal will be 630 meters (3 berths). The Bronka Phase 1 capacity is projected to be 1.45 million TEUs and 260,000 units of Ro-Ro cargoes. The facility’s container throughput is planned to be increased to 1.9 million TEUs. The Bronka Multipurpose Complex will be able to handle Panamax containerships and the ferries of Finnstar class. 

Private investors are expected to inject nearly RUB 43.7 billion in the project with the Russian Government investment at some RUB 15.2 billion.

Implementation of the Bronka project will bring 2,300 work places at sea terminals alone.  Upon completion of the outer harbor facilities annual direct tax payments to the budget of St. Petersburg will be at RUB 1.7 billion (plus indirect tax due to a multiplier effect – RUB 5.1 bn), the federal budget will get RUB 2.0 billion a year (RUB 5.9bn).