In 2015, “Yuzhniy” seaport Authority has launched a plan to attract capital investment in the development of infrastructure, USPA cites the Head of the port authority Maxim Shirokov as saying during a press-conference.
Total amount of capital investment reached 54.0 million UAH of which:
26.0 mio UAH for the purchase of basic assets: incinerator, JSB truck, two vans;
2.0 mio UAH for capital construction works, such as: construction of a pedestrian crossing, and design work for the construction of the port fleet base placement;
26.0 mio UAH for reconstruction of incinerator buildings complex, lightning protection system and the system of heat energy.
The forecast amount of capital investments in the port for 2016 totals 958 million UAH. of which:
112 mio UAH for the purchase of basic assets such as technological equipment and the purchase of oil-clean vessel
31 mio UAH for capital construction works — construction of the port fleet base placement project
815 mio UAH for reconstruction of basic assets such as reconstruction of fire fighting system on specialized berths №№ 3,4, partial reconstruction of the marine approach channel, reconstruction of berths №№ 5–8, the beginning of the project implementation on advanced deep development in “Yuzhniy” seaport.
As part of the project on creation of a perspective depths in “Yuzhniy” seaport in 2016 it is scheduled to start dredging to reach depths of 16 meterstowards the berths group of companies «TIS» and designed construction of the berth № 25 owned by «MB Cargo» Ltd. The summary cost of the project for the dredging totals 3.5 billion UAH. Implementation period of 2 years.