Jan De Nul bags 600MW Kriegers Flak contract

Jan De Nul Group signs a contract with Vattenfall Vindkraft Kriegers Flak P/S for the transport and installation of 72 8.4MW Siemens Wind Turbine Generators (WTG) for the Kriegers Flak Offshore Wind Farm (OWF) in Denmark, the company said in its release.

The Kriegers Flak OWF is located in the Baltic Sea in water depths varying between 15 and 30 metres, at 15 kilometres from shore. In 2017-18, Jan De Nul Group already built, towed and installed two large Gravity Based Foundations for the Offshore High Voltage stations of the Kriegers Flak OWF.

Installation works will start in the first quarter of 2021 and will take four months.