NIBULON сontinues building self-propelled P-140 crane vessel
NIBULON says its shipbuilders have already installed the CBG360 bow crane with the lifting capacity of 45 tons produced by Liebherr-MCCTEC Rostock GmbH on NIBULON MAX. They are preparing to install an aft crane.
Presently, NIBULON’s shipbuilders are finishing insulation of living spaces. They are installing paneling and laying cables.
At the same time, the specialists are producing marine furniture at the joiner’s workshop. On the captain’s bridge, the shipbuilders have completed insulation; they are installing paneling and connecting cables to equipment. The shipbuilders have installed a pilot control console.
The specialists have already started testing main diesel generators and power plant systems in the engine room. NIBULON’s shipbuilders have installed the bow cargo crane produced by Liebherr-MCCTEC Rostock GmbH; they are preparing to install the aft crane. The shipbuilders are assembling hatch covers for two holds. The specialists are outfitting coamings on the guard rails of holds.
The vessel, which will be put into operation in September 2019 as part of the TRANS EXPO ODESA-MYKOLAIV 2019 international forum at the territory of NIBULON shipbuilding and repair yard, was designed and is being built in compliance with the current rules and under the supervision of the Shipping Register of Ukraine.