1. Home
  2. Maritime industry news - PortNews
  3. Transneft Primorsk Port continues works as part of implementation of Sever-25 Project

2016 August 2   09:52

Transneft Primorsk Port continues works as part of implementation of Sever-25 Project

Transneft Primorsk Port continues works as part of implementation of the project “Development of the Trunk Pipelines Systems for Increasing Petroleum Products Supplies to Primorsk Port up to 25 Million Tons a Year” (Sever-25), says Transneft.

Earlier, in 2015, construction and assembly works were as well conducted in the territory of Transneft Primorsk Port at three facilities of the first stage of the Sever-15 Project – increasing the amount of diesel fuel transportation up to 15 million tons. 

Overhaul of two tanks with the amount of 50 thousand cubic metres (VFRT) of the oil depot No. 1 (oil) has been performed and receiving of diesel fuel to them has been secured. Works on laying industrial pipelines related to the first and the second stages of Sever-15 construction have been finished. Total length of the constructed pipelines is equal to 1,731 m. Works on cleaning functioning industrial pipelines and connection of the pipelines of the Oil Depot No. 1 to tanks for diesel fuel receiving have been finished.

The main stage of the investment project Sever-25 started in 2016. At the present time Transneft Primorsk Port conducts the following works as part of the project: reconstruction of Oil Depot No. 1; reconstruction of Oil Depot No. 2 (petroleum products); reconstruction of berths No. 3, 4; reconstruction of berths No. 1, 2, 6, 7; reconstruction of berths No. 8, 9, 10; construction of the oil quantity and quality measuring system; construction of overhead cable tray; assembling of industrial pipelines; assembling of electrical power supply system, assembling of automation system.