Nord Stream’s Deputy Director Construction Ruurd Hoekstra and Leo D. Varkevisser, Allseas’ Vice President Projects and Operations, arrived on board the Solitaire to confirm that everything is on schedule and “all systems go” for the start of construction. Before starting its journey to Russian waters, the Solitaire was adapted to Nord Stream’s requirements in Rotterdam, where each piece of equipment was thoroughly tested in port.
The Solitaire has taken up laying the pipeline 7.5 kilometers from the Russian landfall and will continue in a westerly direction through the Gulf of Finland to kilometer point (KP) 300. Afterwards, in January 2011, the pipe-lay vessel will move on to KP 350 and lay the pipeline back towards KP 300. The Solitaire will also lay the same section of the second string of the pipeline from May to September 2011. The dynamically-positioned Solitaire will operate without anchors in this congested part of the Baltic Sea known for its many historic mine lines.
The section of both strings of the pipeline between Russian landfall and KP 7.5 has already been laid by another pipe-lay vessel, Saipem’s Castoro Sei, which is currently laying the pipeline in Finnish waters in an easterly direction between KP 451 and KP 350.
This complex lay sequence was developed by Nord Stream and agreed with the Finnish and Russian authorities to meet environmental restrictions while making the construction vessels work as efficiently as possible. To give just one example: there will be no construction works in the north-eastern part of the route in winter when it is covered by ice; this also ensures that breeding seals are not disturbed.
Construction of Nord Stream – the most advanced of the new pipelines that Europe will need to meet its future energy requirements – is progressing on schedule and according to plan. Over 250 kilometers of the first pipeline have already been laid in Swedish and Finnish waters. At the Russian landfall in Portovaya Bay, close to Vyborg, and at the German landfall at Lubmin, near Greifswald, both strings of the pipeline have already been constructed and pulled ashore.