Construction of the first phase started end of April 2010 and involved an investment of about € 70 million. Construction was executed by the Polish company Polimex-Mostostal, within budget and on schedule.
BTT has 34 storage tanks, providing a combined storage capacity of 200,000 m3, of which 130,000 m3 is earmarked for clean fuels and 70,000 m3 for edible oils and biodiesel. The terminal’s 420 meter jetty can accommodate two seagoing vessels of up to 115,000 DWT and two barges simultaneously.